CONSTRUCTION UPDATE
As of 03/26/2019, the parking lot at 280 Washington Avenue, Bremerton, WA is closed for construction.
Current Activity: The City of Bremerton is in the process of installing a new force main that runs through the current parking lot (running from the NW to the SE of the site). Due to spacing needed for excavation and concrete pours, jersey barriers were installed along the east side of Washington Avenue, reducing it to a one lane road. These barriers will be up for a large duration of the project. Thank you for your patience and understanding.
Upcoming Activity: Compass Construction (General Contractor for the Marina Square development) is planning on installing fencing around the entire project site starting April 1st, 2019. Within the first 2 weeks, they will begin to mobilize to the site and a jersey barrier will be installed on Washington Avenue (just West of the site). In addition, there will be modifications to the current downtown traffic flow. We will provide an image of those modifications in the coming week.
What To Expect Coming Up:
– Utility Relocation (4/1/19 – 5/1/19)
– Demo (4/1/19 – 5/1/19)
– Mass Excavation (5/1/19 – 6/19/19)
– Temporary Shoring (5/1/19 – 6/19/19)
– Erosion Control (On Going)
– Tower Crane Installation (7/9/19)
Please check back periodically as new information comes available.